Last few days to respond to 1000MW Data Centre

There are only 10 days left to Object to a 1000MW data centre at Chapelcross, it has a deadline of 29 October. The key to writing an effective planning objection is to refer to ‘material planning considerations’. These are matters that the planning authority can take into account when deciding whether the development is acceptable which includes elements of National Planning Framework 4 and the Local Development Plan.

We have written a document to help supporters to object, giving advice and instructions.

  • How to Object to the Proposed 1000MW Chapelcross Data Centre

    If you are concerned about the proposed 1GW data centre at Chapelcross, you can make your views known by submitting a formal objection to Dumfries and Galloway Council. You do not need to be a planning expert, and you do not need to write a long or technical response.

This proposed 1GW (1000MW) data centre development, covering 57 hectares, is planned for land just north of the former Chapelcross nuclear site near Annan, Dumfries and Galloway.

This data centre capacity, at 1000MW, is bigger than any data centre currently operating in the world (EpochAI.) The data centre with the highest IT power in the world in operation is Elon Musk’s Colossus II in Memphis with 946MW of capacity. 

The Chapelcross data centre would use 7 million MWh of energy a year, if operating at the estimated 80% capacity of AI data centres, which is equivalent to almost a third (32%) of all the electricity used in Scotland in 20241

And the same as 2.2 million households, which is 88% of Scottish households.(references for calculations in the data centre calculator)

The developer submitted this vote only 5 days after Parliament voted for a pause on planning decisions on hyperscale AI data centres, while guidance and a strategic approach was put in place. The application does not respect the Parliamentary processes that are currently in place including work in committees, and puts the Scottish Government in a difficult situation. In theory the Scottish Government have said that developers can still put in applications, but they have also agreed that no decisions will be taken until guidance is in place. If this is the case then the processes of decision-making such as the consultation period, the work of the statutory consultees and the work of planning officials on the application, also should wait until t he guidance is in place. Surely any Objection responses, statutory responses etc will need to be revisited once the guidance is in place as it will become a material consideration in he planning application.

Summary of the proposal

The headline figures, all taken from the applicant’s own documents:

  • Eight data centre buildings up to 40 metres tall, roughly the height of a 13 storey block, with a substation up to 15 metres and a training centre and industrial units up to 9 metres.
  • Each data centre building would have up to 42 standby generators, air-cooled chillers, fuel tanks, transformers and batteries.
  • Construction would run for about 8 years, from 2027 to 2035.
  • The main application document does not give the IT capacity of the data centre. Press reports describe it as 1 Gigawatt (1,000 MW). And other documents in the application say there will be eight buildings each “assumed to be 120 MW” (Sustainability Statement). The EIA Report Appendix 15-2 gives it as “640 MW IT load” ; and up to 336 generators of 3,200 kW each which is about 1,075 megawatts of standby generation

No operator or end user is named. The application is for permission in principle (PPP). Approval of the PPP would establish the principle of a data centre on this site, with much of the detailed design dealt with later. We do not believe that a Planning in Principle application is sufficient to understand what is actually being proposed, and the impacts, in such a huge and environmentally damaging development.