In the First Minister’s Questions on 8th October 2026, Gillian Mackay, Leader of the Scottish Green Party questioned The First Minister on the lack of engagement with communities’ views on data centres.
Read the transcript from the Official Report below:
Data Centres (Communities’ Views)
3. Gillian Mackay (Central Scotland and Lothians West) (Green):
The Scottish Government has said that no decision on applications for huge data centre developments should be made until new guidance is in place. However, since that statement, Dumfries and Galloway has seen an application for one of the largest data centres in the world. It would be a monstrosity that would use the same amount of electricity as more than 2.2 million Scottish homes. Five thousand people have objected to it already, but Chapelcross now joins Larbert, Greenock, Auchtertool and 21 other communities across Scotland that are waiting to see whether they will be blighted by huge data centres. What reassurance can the First Minister give those communities that their views will be listened to?
The First Minister (John Swinney):
The best reassurance that I can give is to repeat the commitment that I have given to Parliament on previous occasions, which is that we do not anticipate that any applications will be determined by planning authorities before our planning guidance is issued later this year. I am very confident about the authority of that statement.
Gillian Mackay:
The First Minister’s Government has acknowledged that tech giants are marking their own homework when it comes to applications. In this chamber, he previously referred to an Edinburgh hyperscale data centre as “green”, but the Government later confirmed to us that the reference to it being green was taken directly from the description provided by the applicant. That comes after investigative journalists at The Ferret found that the Scottish Government had been lobbied by industry to use the phrase “green data centre”. Will he now make a concrete commitment to listen to the views of communities, as well as lobbyists, by carrying out a full public consultation on the draft guidance before any planning decisions are made?
The First Minister:
The Government engages with a range of interested parties, and the Government would be criticised if it did not do so. Those parties include members of the community. If my memory is correct, we have called in the application for Edinburgh, and we have indicated that further guidance will be issued. In preparing that guidance, the Government is of course engaging with a variety of different opinions. If we were to undertake a full-scale public
consultation of the scale that is determined by, or requested by, legislation, that would significantly extend the amount of time until the guidance could be made available. That might compromise the commitment that I gave to Parliament, because of the timescales involved. I will consider the issue that Gillian Mackay has raised, but I have to ensure that we take our decisions in an orderly fashion and give guidance to the planning authorities that have legitimate statutory obligations to address in relation to
determining those applications.
Gillian Mackay:
I appreciate the statutory duty that local authorities have, but giving that time would also give the time that would enable communities to have their say on the planning guidance that comes forward. I know from my constituents that the uncertainty around those centres is causing genuine and profound concern. Communities simply do not
know what is going to come along. Councils across the country do not know what is going to come along, and local businesses do not know either. For example, the determination date for the Larbert application lapsed on 4 October. I appreciate what the First Minister says about not anticipating any decisions being made, but that leaves the Larbert community in my region in limbo. Has the First Minister instructed the chief planner to issue directives to councils telling them to pause applications until the Government guidance is in place? If not, when will he do so, to give those communities that certainty?
The First Minister:
The Government engages actively with local authorities to provide advice and
guidance on the consideration of applications. What I and my ministers say in Parliament will be reflected in the communication and interventions of the chief planner, operating within the statutory framework that is appropriate for such decisions. We have a number of statutory obligations to be mindful of, not least those in the contents of national planning framework 4, which has been approved by Parliament on a statutory basis. The Government cannot just ignore the contents of that planning framework. I assure Gillian Mackay that what I am saying in Parliament is being communicated and conveyed to the chief planner to planning authorities.
See: Meeting of the Parliament (Coinneamh na Pàrlamaid) Session 7 Official Report, page p. 19:
On the same day, fifteen of the community groups affected by hyperscale data centre proposals wrote to the Minister for Public Finance, Hannah Mary Goodlad, to call on the Scottish Government to set out how this pause is intended to work, given live applications remain in the planning system, and asked the Minister to meet representatives from the community campaigns.
Read our article about the letter here, and read the letter below:
See: Letter to Hannah Mary Goodlad on Community involvement over Hyperscale Data Centre Guidance and Strategy