This application is for a 213MW data centre at the Gyle in Edinburgh on a site with planning permission for offices and in an area designated for mixed use development with residential and leisure development planned to be built in 2026. The application for planning permission in principle was rejected by the Edinburgh City Council sub-committee responsible for planning decisions in February 2026 and the developer has appealed.

This data centre was turned down by the council and they have appealed to the Scottish Government –
Watch the meeting here and read an analysis of the decision here, and they now have appealed.
Grounds for appeal are summarised here:
The decision document from the council is with the planning documents for the development
The Appeal documents are on the DPEA website The deadline for representations is 28 April 2026
Local Campaign Group
Some local residents have gathered together with a Whatsapp Group and you can join it here.
You can follow the local campaign group on Instagram here.
News related to Edinburgh Development

Yesterday the planning committee of Edinburgh City council met to discuss a moratorium on hyperscale AI data centres and the definition of a ‘green data centre’. They voted for Edinburgh council to call on the Scottish Government for a nationwide moratorium until there is a definition of what a ‘green data centre’ is.

Edinburgh City Councilors will get the chance to vote on whether they put in place a moratorium on new data centres in the city this week.

The developer of a 212MW hyperscale AI data centre at the Gyle Edinburgh which was turned down by the Council Planning Committee in February have appealed the decision.

In this blog post Kat reflects on the decision to refuse a hyperscale data centre in Edinburgh and what this means for future decisions and our data centre campaign. This was first published in Bella Caledonia

A few minutes ago the Development Management sub-committee at Edinburgh City Council refused Planning Permission in Principle for a 210MW data centre at the Gyle, Edinburgh. Here are some observations from the meeting and a statement from APRS.

Communities campaigning against hyperscale AI data centres gathered outside Holyrood (Wednesday 24th June) ahead of Climate and Rural Affairs Parliamentary
Appeal Statement
Planning Application Details
Application for planning permission in principle
25/04239/PPP
the documents related to the EIA screening 25/03575/SCR
Planning Permission in Principle was rejected in February 2026 but the developers could appeal within 6 weeks of the rejection.
Report from the Planning Committee here: https://aprs.scot/press-release/edinburgh-data-centre-refused/
Info last checked – 23 Feb 2026
EIA screening not requested
Business park
Address and Location
1 Redheughs Avenue, EH12 9RH
55.931989°, -3.308918°
Local Authority
Edinburgh
Developer and Size of the site
Shelborn Drummond Ltd
212.42MW