The proposal at the Laundryfield, is for a 300MW Data Centre on farmland near Coldstream in the Borders. They will not be required to do an Environmental Impact Assesment (EIA). The developer is Apatura

Planning References
EIA screening done, awaiting next stage. They are not required to do an EIA
Address and location
The Laundry Field, Coldstream, LAND EAST OF A697, SCOTTISH BORDERS, SCOTLAND, TD12 4LZ
55.683301°, -2.360424°
Size
it says 300MW some places but 500MW on the planning application
150ha. PAN boundary= 252ha
Other news
https://www.datacenterdynamics.com/en/news/apatura-files-for-300mw-data-center-campus-in-scotland